Practice
Resources
Contests
Online IDE
New
Free Mock
Events New Scaler
Practice
Improve your coding skills with our resources
Contests
Compete in popular contests with top coders
logo
Events
Attend free live masterclass hosted by top tech professionals
New
Scaler
Explore Offerings by SCALER

Greedy Algorithm

Last Updated: Nov 17, 2023
Go to Problems
locked
Greedy Algorithm
info
Complete all the problems in this Topic to unlock a badge
Completed
Go to Problems

Level 1

Jump to Level 2

Level 2

Jump to Level 3

Level 3

Jump to Level 4

Level 4

Jump to Level 5

Level 5

Jump to Level 6

Level 6

Jump to Level 7

Level 7

Jump to Level 8

Level 8

Be a Code Ninja!
Contents

How to Create Greedy Algorithms?

How to Create Greedy Algorithms?

A greedy algorithm makes the choice that appears best at that instance of time with the hope of finding the best possible result. In general, the greedy algorithm follows the below four steps:

  • Firstly, the solution set (that is supposed to contain answers) is set to empty.
  • Secondly, at each step, an item is pushed to the solution set.
  • Only if the solution set is deemed feasible, the current item is kept for future purpose.
  • Else, the current item is rejected and is never considered again (no reversal of decision)

Let us understand this by considering some examples.

1. Maximising Number of Tasks:

Case Study:

Imagine you are a very busy person and you have lots of interesting things to be done within a short span of time T. You would want to do maximum of those interesting todo things in the short time you have.

You have a integer array A, where each element ai represents the time taken to complete a task. Your main task is now to compute the maximum number of things that can be done in the limited time T.

Analysis:

By carefully observing the problem, we can say that this problem requires nothing but a simple application of Greedy algorithm. Our natural greedy instinct says that in order to accomplish maximum tasks, we have to do the tasks that require minimum amount of time.

  • In every iteration, we greedily select the tasks which takes minimum completion time. This is achieved by maintaining two variables currentTime and numberOfTasks. In order to solve this problem, we follow the below steps:
    • Sort the given array A in ascending order.
    • Select a to-do task one-by-one.
    • Add the time taken to complete that task to the currentTime variable.
    • Increment numberOfTasks by 1.
    • Repeat this until currentTime <= T.
  • Let array A = {4, 2, 1, 2, 5} and fixed time T = 8
    • After sorting the array, A = {1, 2, 2, 4, 5}
    • 1st iteration:
      • currentTime = 1
      • numberOfTasks = 1
    • 2nd iteration:
      • currentTime = 1 + 2 = 3
      • numberOfTasks = 2
    • 3rd iteration:
      • currentTime = 3 + 2 = 5
      • numberOfTasks = 3
    • 4th iteration:
      • currentTime = 5 + 4 = 9 > T. Therefore, stop looping.
    • Hence, the final answer is 3.

Java Implementation:

import java.util.*;
public class InterviewBit{
    public static int maximiseTasks(int[] A, int T){
        Arrays.sort(A);
        int currentTime =0;
        int numberOfTasks = 0;
        for(int i = 0;i < A.length;i++)
        {
            currentTime+= A[i];
            if(currentTime > T)
                break;
            numberOfTasks++;
        }
        
        return numberOfTasks;
    }
    public static void main(String[] args){
        Scanner s = new Scanner(System.in);
        int N = s.nextInt();
        //Time limit
        int T = s.nextInt();
        //populate A array
        int[] A = new int[N];
        for(int i =0;i<N;i++){
            A[i] = s.nextInt();
        }
        
        int result = InterviewBit.maximiseTasks(A,T);
        System.out.println("Maximum number of tasks achievable: " + result);
    }
    
}

2. Fractional Knapsack Problem:

Case Study:

Given weights and values of n items and the flexibility that you are allowed to break items or choose fraction of the items. Your task is to put these items in a knapsack of capacity W to get the maximum total value of the items in the knapsack.

Input: 
Number of items, n = 3
int[] weights = { 10, 20, 30 }; 
int[] values = { 60, 100, 120 }; 
int capacity = 50; 

Output: 
Maximum Value Attainable - 240 
Considering items of weight 10 kg and 20 kg and 2/3 fraction of 30 kg. 
Hence total price will be 60+100+(2/3)(120) = 240

Analysis:

Brute Force:

The brute force approach that comes to our mind first is to try all possible subset with all different fraction and then choose the best out of it. This approach is really time consuming and the time complexities could be exponential.

Efficient Approach:

The efficient approach that can be used is to use Greedy Approach.

  • The main idea of this approach is to calculate the ratio value/weight for each item and then sort the items on basis of this ratio.
  • Then, from this sorted list, take the item with the highest ratio and add them until we can’t add the next item as a whole. At the end, add the next item as much as we can.
  • This will ensure that the solution will always be the optimal to this problem.

Java Program:

import java.util.Arrays; 
import java.util.Comparator; 
  
public class IBFractionalKnapsack  
{ 
    // function to get maximum value attainable 
    private static double getMaxValue(int[] weights, int[] val, 
                                      int capacity) 
    { 
        WeightValue[] weightValue = new WeightValue[weights.length]; 
        // Populate with the values
        for (int i = 0; i < weights.length; i++) { 
            weightValue[i] = new WeightValue(weights[i], val[i], i); 
        } 
  
        // sorting items by value/weight ratio; 
        Arrays.sort(weightValue, new Comparator() { 
            @Override
            public int compare(WeightValue o1, WeightValue o2) 
            { 
                return o2.ratio.compareTo(o1.ratio); 
            } 
        }); 
  
        double totalValue = 0d; 
  
        for (WeightValue i : weightValue) { 
  
            int curWeight = (int)i.weight; 
            int curValue = (int)i.value; 
  
            if (capacity - curWeight >= 0)  
            { 
                // this weight can be picked while 
                capacity = capacity - curWeight; 
                totalValue += curValue; 
            } 
            else 
            { 
                // item cant be picked whole 
                double fraction 
                    = ((double)capacity / (double)curWeight); 
                totalValue += (curValue * fraction); 
                capacity 
                    = (int)(capacity - (curWeight * fraction)); 
                break; 
            } 
        } 
  
        return totalValue; 
    } 
  
    // Weight value class 
    static class WeightValue  
    { 
        Double ratio; 
        double weight, value; 
  
        // item value function 
        public WeightValue(int weight, int value) 
        { 
            this.weight = weight; 
            this.value = value; 
            ratio = new Double((double)value / (double)weight); 
        } 
    } 
    
    // Driver code 
    public static void main(String[] args) 
    { 
        int[] weights = { 10, 20, 30 }; 
        int[] values = { 60, 100, 120 }; 
        int capacity = 50; 
  
        double maxValue = getMaxValue(weights, values, capacity); 
        
        System.out.println("Maximum Value Attainable - "
                           + maxValue); 
    } 
}

3. Task Scheduling:

The previous example of maximising number of tasks was quite simple. We could easily understand how greedy approach could be applied to solve the problem. Let us focus on a more complicated example which is the problem of task scheduling based on priorities of each work. Note that a work (or a job) requires one or more tasks for completion.

Case Study:

The problem statement states that we have the following information:

  • Total jobs to be done- N
  • List of jobs that has to be done by today - J
  • List of all the tasks that has to be completed by today for each job
  • Time duration required to complete each task ( T )
  • Weight or Priority of each task. ( P )

You need to determine in what order you should complete the tasks to get the most optimum result. What is the condition for the optimal scheduling of tasks? Can priority[i] can be applied to any job J or just to J[i]? Let us find answers to these questions in depth in the upcoming “Analysis” section

Analysis:

Let us start by analysing our inputs. We have J as the number of jobs that has to be done today. T as the list of time duration of each task and P is the list of priorities assigned to each task.

  • To understand the criteria that needs optimisation, we must first compute the total time taken to complete each task for a job Ji.
    • Mathematically, J(i) = T[1] + T[2] + .... + T[i] where 1 <= i <= N
    • The i-th work has to wait till the first (i-1) tasks are completed after which it requires T[i] time for completion.
    • Consider this example, given that T = [1, 2, 3], the completion time for a job will be:
      J(1) = T[1] = 1
      J(2) = T[1] + T[2] = 1 + 2 = 3
      J(3) = T[1] + T[2] + T[3] = 1 + 2 + 3 = 6
      
    • We obviously want completion times of the jobs to be as less as possible.
    • In a given job sequence, let us assume that the jobs queued up at the beginning require shorter time to complete and the ones that are queued up at the end require longer time to complete.
    • Now, what can be the optimal method to complete the tasks?
      • Well, this depends on our objective functions (final goal states after executing tasks). There are many objective functions available in the “Scheduling” problems. But in case of our example, the objective function F would be the weighted sum of the completion times of the job. Mathematically, the expression becomes: F = (P[1] * J(1)) + (P[2] * J(2)) + ...... + (P[N] * J(N))
      • Our main task is now to optimise this object function.
  • Now that we have established what is the criteria for optimisation, let us see how this problem can be solved. Considering the given objective function, we have the following cases which needs to be considered while minimising the function.
  • The main rule for optimising the objective function in these special cases is to give preference to the tasks:
    1. 1. having higher priority
    2. 2. taking lesser completion times
  • Natural Intuition:
    • Let us consider reasonably intuition of optimising our objective function. Just by doing this, we can come up with several greedy algorithmic tactics and then based on careful analysis, we can narrow down to what tactic works best and why it works the best.
    • The two special cases that can be thought of by doing natural intution are:
      • If the priorities of different tasks are the same i.e. P[j] = P[k] where 1 <= j, k <= N but they take different time durations to complete, then in what order do can we schedule the jobs?
      • If the time taken to complete different tasks are the same i.e. T[j] = T[k] where 1 <= j, k <= N, but those tasks have different priorities assigned, then in what order can we schedule the jobs?
    • By evaluating the above listed special cases, if 2 or more tasks take same time to complete, then the task with higher priority is given more preference.
    • Case 1: Tasks taking same time to execute but different priority
      • Consider the objective function we deduced and also assume that the time required to complete the different tasks is t i.e T[i] = t where 1 <= i <= N
      • Irrespective of the sequence of tasks, the completion time would be same for each task and the equations become:
        J(1) = T[1] = t
        J(2) = T[1] + T[2] = 2 * t
        J(3) = T[1] + T[2] + T[3] = 3 * t
        J(4) = T[1] + T[2] + T[3] + T[4] = 4 * t
        :
        :
        J(N) = N * t
        
      • To minimise/optimise the objective function, it is natural that the highest priority task must be associated with the shortest completion time.
    • Case 2: Same priorities but different completion time:
      • In this case, it is obvious that we must choose the task that takes least time of completion. Let us assume that the priorities of the tasks is p. Then our minimised objective function becomes:
        F = (P[1] * J(1)) + (P[2] * J(2)) + ...... + (P[N] * J(N))
        F = (p * J(1)) + (p * J(2)) + ...... + (p * J(N))       //Since P[i] = p 
        F = p * (J(1) + J(2) + ...... + J(N))
        
      • To minimize F, we now must minimize focus on minimising (J(1) + J(2) + ...... + J(N)), which is possible only if we start to work on the tasks that require the shortest completion time.
  • General Case: Different Priorities, Different Completion Times
    • In this case, the priorities and the completion times of each task are totally different. This is the most common scenario that usually occurs.

    • Consider the scenario where you have 2 or more tasks and the main rules of choosing tasks i.e we select the task that has higher priority and shorter completion time first. But what if this results in conflict? Assume that we have tasks where one of them has higher priority but longer completion time and the other one has least priority and shorter completion time? ( i.e. P[1] > P[2] and T[1] > T[2] ). Which task should be completed first?

    • We can think of aggregating the varying parameters (completion time and the task priority) into a single defining parameter so that based on this parameter, we can schedule the tasks in a optimal manner. Now what should this parameter be?

      • By using the rules of selecting tasks, we can come up with a simple function that takes 2 parameters - time and priority - as input and return a single judging parameter as output that combines the properties.
      • We can look into the following 2 algorithms:
        • Algo #1: Schedule the jobs based on the decreasing value of (P[i] - T[i])
        • Algo #2: Schedule the jobs based on decreasing value of (P[i] / T[i])
      • Since we have 2 algorithms, we can say that atleast one of the algorithms is wrong. Let’s see which one.
        • Consider T = [7, 3] and P = [5, 2]
        • As per Algo #1, (P[1] - T[1]) < (P[2] - T[2]) . Hence second task can be completed first. The objective function becomes:
          F = (P[1] * J(1))+ (P[2] * J(2)) = (2 * 3) +(5 * (7+3)) = 56
          
        • Now, based on Algo #2, (P[1] / T[1]) > (P[2] / T[2]). Hence, the first task can be completed first. The objective function becomes:
          F = (P[1] * J(1)) + (P[2] * J(2)) = (5 * 7) + (2 * (7+3)) = 55
          
        • We can see that the result from Algo #2 is lesser than the result obtained from Algo #1. Hence, we can consider that Algo #1 does not give us the optimal answer. This also concludes that the results from Algo #1 doesnt always gives the correct answer.

      Pseudo-Code based on Algorithm 2:

      /**
      * Let S = array of pairs to store the scores and their indices
      * J = completion times of job
      * F = objective function
      * P = List of priorities
      * T = time taken of task
      * N = number of job
      */
      ObjectiveFunctionF (P, T, N)
          {
              for i from 1 to N:
                  S[i] = ( P[i] / T[i], i ) 
              
              Arrays.sort(S)
              J = 0
              F = 0
              for i ranging from 1 to N:         // Greedy selection
                  J = J + T[S[i].second]
                  F = F + P[S[i].second]*J
              
              return F
          }
      
      • Time Complexity: The time complexity of this algorithms is O(N*logN) because we have 2 loops that takes O(N) time each and one sorting functionality which takes O(N * logN). Hence, O((2 * N) + (N*logN)) = O(N*logN).

      Proof of correctness of Algo #2:

      • Let us try to prove why Algo #2 is the best and correct approach for task scheduling by means of proof by contradiction i.e by assuming the thing we are trying to prove is false and in that process derive that the thing we assumed earlier was originally correct.
      • Let us assume that Algo #2 does not give optimal solution and there is another non-greedy algorithm which gives us an even more better solution.
        • G = Greedy schedule (which is assumed as non-optimal schedule)
        • O = Optimal Schedule (Non-Greedy approach)
      • Consider the below 2 assumptions:
        1. 1. (P[i] / T[i]) is different.
        2. 2. ( P[1] / T[1] ) > ( P[2] / T[2] ) > .... > ( P[N] / T[N] ) 
      • Because of assumption #2, the greedy schedule will be G = ( 1, 2, 3, ....., N ). Since G is considered as non optimal and G is not equal to O, we can say that O must contain two consecutive jobs (i,j) in such a way that i > j. This is true as the only schedule that has the indices increase monotonically is G = ( 1, 2, 3, ...., N ) Therefore, O = ( 1, 2, ..., i, j, ... , N ) where i > j.
      • We also need to consider what is the profit or loss impact in case of swapping 2 jobs. Let us see what is the effect due to the below swapping:
        • Work on task k other than i and j
        • Work on task i and then
        • Work on task j
      • For task k now there will be 2 cases:
        • When k lies on left of i and j in O, while swapping tasks i and j, there is no effect on the completion of task k since J(k) = T[1] + T[2] + ..T[k]+.. + T[j] + T[i] + .. 
        • When k lies on the right of i and j in O, after the swap, the completion time of k is J(k) = T[1] + T[2] + .. + T[j] + T[i] + .. T[k]+..k will again remain the same.
      • For task i, the completion time before swap was J(i) = T[1] + T[2] + ... + T[i] and after swap is J(i) = T[1] + T[2] + ... + T[j] + T[i]. As we can see, clearly, the completion time of i went up by T[j] and there by deduce that the completion time for j goes down by T[i]. Due to swap:
        • Loss is (P[i] * T[j])
        • Profit is (P[j] * T[i])
      • Using the second assumption, i > j signifies (P[i] / T[i]) < (P[j] / T[j]). Therefore, we have (P[i] * T[j]) < (P[j] * T[i]) which means that the Loss < Profit. This signifies that the swap effect improves algorithm O further but this contradicts the initially assumed fact that O is already an optimal schedule. Hence, we can say that greedy approach gave us the optimal algorithm.

Greedy Algorithm Applications

Though greedy algorithms don’t provide correct solution in some cases, it is known that this algorithm works for the majority of problems. However, greedy algorithms are fast and efficient which is why we find it’s application in many other most commonly used algorithms such as:

  • Dijkstra’s Algorithm: This algorithm is the most famous graph traveral one that is used for finding the shortest path between nodes in a graph.
  • Minimal Spanning Tree (MST): This algorithm is widely used in Cluster Analysis, Handwriting recognition and Image segmentation.
  • Huffman Coding: This is the most common algorithm in the field of data compression. It analyzes a given message and based on the frequencies of the characters present in the message, a variable-length code for each symbol is assigned.

The most basic purpose of greedy algorithm is optimisation which can be either minimisation or maximisation based on our problem statement requirements.

FAQs

What is the time complexity of a greedy algorithm?

  • The time complexity of a greedy algorithm depends on what problem you are trying to solve, what is the data structure used to represent the problem, whether the given inputs require sorting and so many other factors.
  • The most common time complexities of commonly solved problems are:
    • Activity Selection Problem
      • With Unsorted Activities: O(n * log n)
      • With Sorted Activities: O(n)
    • Dijkstra’s Shortest Path Algorithm: V= Nodes, E= Edges
      • Matrix Representation: O(V2)
      • Adjacency List: O(E * log V)

Is Dijkstra a greedy algorithm?

  • Yes.

Are greedy algorithms optimal?

  • Greedy algorithms are simple and intuitive way of solving any problems which attempt to find the optimal solution. But there are some cases when using greedy algorithms leads to incorrect results. Hence, these are not always optimal.

Is greedy an heuristic algorithm?

  • Heuristic algorithms are the ones that make choices that are known to be theoretically suboptimal but produce reasonable results during practical implementations.
  • Greedy algorithm is just an example of heuristic algorithm. The vice versa is not true.

Does greedy always work?

  • Greedy fails to give optimal and correct results in some scenarios because it attempts to find the overall optimal solution just by finding locally best solution at a particular instant and not by operating exhaustively on the dataset given.

Why does the greedy algorithm fail?

  • Sometimes greedy algorithms fail to find the globally optimal solution because they do not consider all the data. The choice made by a greedy algorithm may depend on choices it has made so far, but it is not aware of future choices it could make.

How do you identify greedy algorithms problems?

  • For a greedy approach to work correctly, we must have a problem that has the below 2 components:
    • Optimal substructures: The optimal solution for the problem lies in the optimal solutions to the sub-problems.
    • Greedy property: The choice that appears to be the best at that moment for all the sub-problems, leads us to an overall optimal solution by never reconsidering our earlier decisions. Read More

Why is greedy algorithm called greedy?

  • In this algorithm, it is believed that the locally best choices made would be leading towards globally best results without reconsidering the previously made choices again. Hence, a greedy algorithm is called as “greedy”.

Video Courses
By

View All Courses
Excel at your interview with Masterclasses Know More
Certificate included
What will you Learn?
Free Mock Assessment
Fill up the details for personalised experience.
Phone Number *
OTP will be sent to this number for verification
+65 *
+65
Change Number
Graduation Year *
Graduation Year *
1994
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
*Enter the expected year of graduation if you're student
Current Employer
Company Name
College you graduated from
College/University Name
Job Title
Job Title
Engineering Leadership
Software Development Engineer (Backend)
Software Development Engineer (Frontend)
Software Development Engineer (Full Stack)
Data Scientist
Android Engineer
iOS Engineer
Devops Engineer
Support Engineer
Research Engineer
Engineering Intern
QA Engineer
Co-founder
SDET
Product Manager
Product Designer
Backend Architect
Program Manager
Release Engineer
Security Leadership
Database Administrator
Data Analyst
Data Engineer
Non Coder
Other
Please verify your phone number
Edit
Resend OTP
By clicking on Start Test, I agree to be contacted by Scaler in the future.
Already have an account? Log in
Free Mock Assessment
Instructions from Interviewbit
Start Test